We installed the client’s new production line in a Jüri production building, from equipment layout through to start-up.

Powder coating line installation with an overhead conveyor
Illustrative photo of similar Maintest work

Project overview

The client built a new production building in Jüri and needed an entire production line installed there from scratch.

The work covered placing the line’s machines according to the production layout, connecting them to each other, and synchronizing the whole line into one working whole.

How the installation went

We started by finalizing the equipment layout together with the client, taking into account the dimensions of the production space and the logic of the production process.

The equipment was positioned, fixed in place and connected to the electrical and pneumatic systems. The automation was configured so that the different parts of the line work in sync with each other.

Before handover to the client, we tested the line at full load, checked the safety systems and made the necessary adjustments to the configuration.

As a result, the client got a ready-to-run production line in the new building that met the planned productivity and quality requirements.

Read more about our industrial equipment installation service or see all completed projects.

Dust collector and ductwork at a powder coating line
Dust collector and ductwork at a powder coating line
Paint booth assembly in a large production hall
Paint booth assembly in a large production hall
New production hall prepared for equipment installation
New production hall prepared for equipment installation

Planning a similar project?

Contact us — we will reply as soon as possible.