Shutdown Planner
Plan a maintenance shutdown’s task sequence, parallel tracks and total cost.
General inputs
Shutdown tasks
| Task | Duration, h | Track | Crew, people |
|---|
Result: shutdown plan
Want help planning a detailed shutdown schedule and crew?
Request shutdown planning supportHow the calculation works
The planner contains 8 editable shutdown tasks (lockout, cleaning, dismantling, inspection, repair, reassembly, idle test, start-up and handover). Each task has a duration in hours, a track (1–3, representing parallel crews) and a team size. The critical path is the longest track total; labour cost = duration × team × hourly rate; downtime cost = critical path × downtime cost per hour.
Example: with all 8 tasks on one track, the shutdown lasts 36 hours. Moving one 4-hour task to a second track shortens it to 32 hours.
Frequently asked questions
What is the critical path?
The longest sequential chain of tasks, which determines the total length of the shutdown.
How can I shorten a shutdown?
Split tasks onto parallel tracks, prepare materials and spare parts in advance, and lock out the machine early.
Does the calculation include contingencies?
No, it is a baseline plan. Add a time buffer according to the age of the machine and the risk of the work.