Changeover Loss Calculator
Calculate the annual value of reducing your changeover time toward a SMED target.
Current changeover time
Production value
Result: changeover loss calculation
Want to reduce changeover time and loss?
Request a production line optimizationHow the calculation works
The calculation is based on SMED logic: minutes saved = current − target time; annual hours saved = minutes ÷ 60 × changeovers per week × weeks per year; annual value = hours × loss per hour. You also see the current and target loss per year.
Example: 10 changeovers a week, 45 min now, 20 min target, EUR 300/h and 48 weeks give 25 min saved per changeover, 200 h a year and a saving of EUR 60,000; the current loss is EUR 108,000 a year.
Frequently asked questions
What is SMED?
A method for shortening changeover time by separating the work that can be done while the machine is running.
How much time is realistic to save?
It depends on the machine and process. Set a target time your team can assess.
How can I speed up changeovers?
Standardise the work, prepare tools in advance and use quick-release fixings.